A11 Bruges

arrow_down
  • A11 BRUGES

    BELGIUM (MSS M35-I) 2014-2017

A11 Bruges

BELGIUM (MSS M35-I) 2014-2017

Location
Bruges, Belgium
Year
2014-2017
Client
Project
Type: Two parallel viaducts, total length of 1950m (6397 ft.)
Typical Span: 35 m (114 ft)
Deck width: 18,3 m (60 ft.)
Typical Cross Section: Slab
Equipment features
Model: MSS M35-I
Construction Type: In situ (In Place)
Type: Underslung MSS
OPS System: Integrated
Performance: 8-day cycles
Challenges
• Construction time with very strict planning
• The Client wanted an automated and industrial process
• Pre-defined design without any adaptation possibilities
Solutions
• Adaptation of the equipment to industrialised cycles, fully ensuring the design specifications
Results
• Construction Period: 91 weeks (Including 6 assemblies and 6 disassemblies)
• Fast construction: Cycles of 8 days, highly industrialised process
• High construction quality and deformation control
• High safety levels during construction
• Total adjustment to the constructive process proposed by the Bridge Designer: Integral Bridge