M30x2-S, currently operating in Rodoanel East, São Paulo, Brasil, is exceeding all expectations building more than ½ kilometre of bridge per month. The works are proceeding normally. The Machine 1, operating since June has finished the 14th spam and the Machine 2, operating since September has finished the 9th spam, with two weekly working cycles for spans of 30 meters each.
Berdnews

Stay up to date with our latest news
Your email is safe with us, we don't spam

Click the Privacy Policy link to read it.