LG 50/ 100, that ended the execution of the Northern section of Laguna Bridge in the end of April, is already constructing the first span of the Southern section of this bridge. The Launching Gantry was dismantled in parts, the biggest possible, in order to allow its transportation by road, being that it was dismantled, transported and reassembled in only 2 months. BERD managed, once more, to go beyond the client’s expectations, having saved, until now, approximately 4 weeks to construction, dismantling, transportation and reassembling time. The Southern section of Laguna Bridge, with 15 spans, is predicted to be concluded in the end of October this year.