BERD’s M45-S, which is currently in Slovakia working on its 3rd project, finished recently the construction of one more viaduct. The equipment was transferred to the second viaduct, with all mains truss assembled. The distance of 330 m was done using concrete blocs placed on the ground. These concrete blocks worked as temporary foundations to support the pier frames. Each step or launching took approximately 3 days. M45-S is starting the construction of its 4th bridge.