  • ESLOVÁQUIA (MSS M70-S) 2010-2011

    CREEK VALLEY

    SLOVAKIA (MSS M70-S) 2010-2011

Creek Valley

SLOVAKIA (MSS M70-S) 2010-2011

Location
Nitra, Slovakia
Year
2010-2011
Client
Project
Type: Viaduct, total length 957m (3139 ft.) (construction with MSS: 702m - 2303 ft.)
Typical Span: 69 m (226 ft.)
Deck width: 25,66 m (84 ft.)
Typical Cross Section: Box (in two stages)
Equipment features
Model: MSS M70-S
Construction Type: In Place
Type: Overhead
OPS System: Integrated
Performance: 20-day cycles (2 stages)
Challenges
Finding a solution that would eliminate temporary structures and build the span that the designer intended (approximately 70m - 229 ft.)
Solutions
Overhead Movable Scaffolding System M70-S (capacity for spans up to 70m - 229 ft.), previously used in Valencia
On the basis of the study carried out with BERD, the bridge Designer opted for a 69m (226 ft.) typical span
Results
Construction period: 55 weeks
Construction faster than predicted in the initial project
Optimisation – no need for construction and demolition of provisional structures
Increased industrialization and easier operationally vis-à-vis the alternatives
Higher construction quality due to the reduction and control of deflections
OPS System allowed the cast of the box in two phases, without any danger of cracking
Final reduction on the cost construction of the optimised viaduct compared to the initial project.