A6 Neckar Bridge

arrow_down
  • A6 NECKAR BRIDGE

    GERMANY (MSS M38-I) 2017-2021

A6 Neckar Bridge

GERMANY (MSS M38-I) 2017-2021

Location
Heilbronn, Germany
Year
2017 - 2021
Project
Type: Bridge, two parallel decks, total length of 1644 m (5394 ft.)
Typical Span: 38 m (125 ft.)
Deck width: 21 m (69 ft.)
Typical Cross Section: TT Slab
Equipment features
Model: MSS M38-I
Construction Type: In situ (In Place)
Type: Underslung MSS
OPS System: Integrated
Performance: 10-day cycles
Challenges
• Very heavy deck
• Bridge crossing crucial road open to traffic, implying totally safe operation
• Demanding work cycle
• Relevant inactive time between the 2 decks construction
• Turnkey solution required: machine + operation
• First Span built over existing road – limited time for operations during road closure
Solutions
• Specific solution for cross beam concreting system
• Adaptation of the equipment to industrialized cycles, fully ensuring the bridge design specifications
• Protective measures to improve safer operation
Results
• Fast construction: cycles of 9 days
• Highly industrialised construction process
• High construction quality and deformation control
• High safety levels during all construction, especially in the first spans, built over a road open to traffic