    OPATOVICKY CANAL

    CZECH REPUBLIC (MSS M45-S) 2010-2011

Opatovicky Canal

CZECH REPUBLIC (MSS M45-S) 2010-2011

Location
Pardubice, Czech Republic
Year
2010-2011
Client
Project
Type: One viaduct, two parallel decks, length of 253,5m (831 ft.) + 223,9m (734 ft.)
Typical Span: 41.5 m (136 ft.)
Deck width: 13 m (42 ft)
Typical Cross Section: PI (π)
Equipment features
Model: MSS M45-S
Construction Type: In Place
Type: Overhead MSS
OPS System: Integrated
Performance: 14-day cycles
Challenges
• Construction of two parallel bridge decks identical to the ones made by the Movable Scaffolding System M45-S in its first project (Sokolov-Tisova).
Solutions
• Due to the similarity of the bridge decks, the natural choice was to use the same constructive method by refurbishing the M45-S.
• A safe choice proven in the past, economic and with a guaranteed deadline
Results
• Construction period: 34+34 weeks
• Fast construction
• High construction quality and deformation control
• High safety levels during construction
• The transversal movement of the machine for the construction of the second deck was an easy operation due to its reduced weight